WBE Lynton Station

Job Title: Wood Buffalo Extension Project- Lynton Station

Client: Enbridge Pipelines (Athabasca)

Approximate Value: $1,400,000.00

Location of Work: Fort McMurray, Alberta Area

Year Completed: 2016

Scope of Work: Excavate for existing pump building concrete floor slab extension. Form and pour floor slab, grade beams, and pump pedestal for building extension and pump addition. Installation of steel pilings for VFD building addition. Install new 5kV VCB in existing substation, including concrete foundation extension, and up-sized feeders to new station transformer to accommodate additional station loads. Install structural and mechanical piping and E&I inside pump building for new pump addition.