Job Title: Cheecham Surmont 2 Project
Client: Enbridge Pipelines
Approximate Value: $27,000,000.00
Location of Work: Cheecham, Alberta
Year Completed: 2015
Scope of Work: Expanding on the existing Cheecham Terminal, work involved the construction of two storage tank foundations requiring the stripping of topsoil, cut and fill to grade, HDPE liner and containment installation, and the construction of the aggregate foundations for the two 500,000 BBL tanks. Also constructed, was a wet pond complete with outfall structures, as well as firewater piping installation and fencing.